Project 1. Wynyard Walk Canopy

This project is a creative steel Structure canopy in the heart of Sydney city.

All the structure steel elements are exposed. Connection detail was designed to be invisible. The perimeter ring beam was made from fabricated boxed plates Curved in two directions.

A specially fabricated secondary structure was designed and fabricated to enable the assembly.

Project 2. Winsor road Railway Bridge – Northwest Rail Link  -Towers

Designed to carry the metro train every four minutes in the peak when Sydney Metro, the Bridge is similar in design to Sydney’s Anzac Bridge – but the first cable-stayed railway bridge built on a curve in Australia.

The bridge’s two towers, with reach 45m above Windsor Rd, were installed in May 2017 then each filled with 336 tonnes of concrete. The bridge deck is supported by 127 steel cables.

The bridge is now a symbol of Sydney’s public transport future,